From investment planning to implementation: DIIP, IP and project documentation
When a need arises for construction, refurbishment or another investment, it is not sensible to begin preparing all of the documents straight away. First, the problem and the objective of the project must be defined, then it must be verified whether the envisaged solution is sensible and feasible, and only after that should it be designed in greater detail and prepared for implementation.
In doing so, we encounter two sets of documentation. Investment documentation substantiates why the investment is necessary, which solution is the most suitable, how much it will cost, how it will be financed and what effects it will deliver. Project documentation, on the other hand, develops the solution technically and determines what will be built and how the construction will be carried out. The two sets of documentation complement one another, but neither can replace the other.
Investment documentation
The Investment Project Identification Document (DIIP) is the first step in appraising an investment
Before the DIIP is prepared, the complete project documentation need not yet be in place. However, at a minimum the purpose of the project, its basic characteristics, the anticipated scope and an initial cost estimate must be known. In construction projects, these data are typically defined with the help of the designer or other experts, who prepare the initial technical or conceptual basis. The DIIP is drawn up on these foundations. It is the first investment document, in which the following are defined:
- the existing situation and the problem that the investor wishes to resolve,
- the purpose and objectives of the investment,
- the basic possibilities or options for implementation,
- the anticipated scope of the project,
- the indicative value and sources of financing,
- the anticipated time for preparation and implementation,
- the expected results and effects,
- the further documentation and procedures required.
The DIIP does not yet mean that the project has been definitively approved and is ready for implementation. Its purpose is, above all, to answer the question of whether the investment intention is sufficiently justified to make continuing the preparation of the project worthwhile. On the basis of the DIIP, the investor decides whether to continue, supplement, amend or abandon the project. The DIIP is therefore not merely an annex to a funding application, but the professional basis for the first decision on the further development of the investment.
The Pre-Investment Design (PIZ) helps to select the most suitable solution
For larger projects, a PIZ is also prepared. In it, the feasible options are compared in greater detail, for example different locations, building sizes, technical solutions or methods of implementation. The comparison covers the costs, benefits, implementation time, risks, impacts and other constraints of each possibility. The purpose of the PIZ is to substantiate which option is the most suitable for the investor. The PIZ is therefore not simply a more extensive DIIP, but a document that enables a considered choice of the solution that will go on to be designed and financially worked up.
The Investment Programme (IP) is the basis for the final investment decision
The IP is prepared for the selected solution once the project is already substantially more developed than at the time the DIIP was produced. At that point, the technical solution, the scope of works, the estimated value, the sources of financing, the implementation time and the manner of organising the project must be determined with sufficient reliability. The IP sets out in greater detail:
- the selected solution and the reasons for it,
- the investment value of the project,
- the financing structure and the financing schedule,
- the financial and economic appraisal of the project's justification,
- the timetable for preparation and implementation,
- the organisation of the project and the responsibilities of those involved,
- the expected results, benefits and effects,
- the risks that could affect implementation.
Its purpose is to verify whether the selected project is technically, financially, economically and organisationally feasible. The IP is therefore the professional basis for the final investment decision. If the scope of the project, its value, the deadlines, the technical solution or the sources of financing subsequently change substantially, it must be verified whether a revision of the investment programme is required.
The difference can be summarised most simply as follows: the DIIP verifies whether it is sensible to continue with the project, whereas the IP verifies whether the selected solution is sufficiently developed and ready for approval and implementation.
Thresholds for the preparation of investment documentation
The Uredba o enotni metodologiji za pripravo in obravnavo investicijske dokumentacije na področju javnih financ (Decree on the uniform methodology for the preparation and consideration of investment documentation in the field of public finances) determines which documentation is required according to the estimated value of the project at constant prices, inclusive of VAT shown separately:
- below EUR 300,000: a DIIP is required for technologically demanding projects, investments with significant financial consequences, or projects that are co-financed from budgetary resources,
- from EUR 300,000 to EUR 500,000 inclusive: at least a DIIP must be prepared,
- above EUR 500,000: a DIIP and an IP are prepared,
- above EUR 2,500,000: a DIIP, a PIZ and an IP are prepared.
For projects with a value below EUR 100,000, the content of the investment documentation may be simplified accordingly. Where an IP is not mandatory given the value of the project, the DIIP is supplemented with additional content and is deemed to be the investment programme, that is, a DIIP/IP. The decree applies to investment projects and other measures that are financed under the regulations governing public finances. For private investments, its requirements are taken into account primarily where they are connected with public financing or are prescribed by the funding call or the financier.
Project documentation
Project documentation develops the solution technically. It is produced by the designer, with whom the investor concludes a written contract. The designer may be a company or an individual that engages the appropriate authorised architects, civil engineers and experts for mechanical and electrical installations and other fields. Project documentation is therefore, as a rule, the result of the coordinated work of several disciplines.
In a typical construction project, we most frequently encounter the following types of project documentation:
- DPP (documentation for obtaining project and other requirements): it is prepared where requirements must be obtained from the competent statutory consultees that the designer must take into account in the further design;
- DGD (documentation for obtaining opinions and the building permit): it presents the planned works in sufficient detail for the statutory consultees to verify compliance with the regulations and for the competent authority to decide on the issue of the building permit;
- PZI (documentation for the execution of construction): it contains the detailed designs, technical solutions and other data that the contractor requires in order to carry out the works;
- PID (documentation of completed works): it depicts the actual as-built state of the structure and is important in obtaining the occupancy permit and in the subsequent maintenance of the structure.
In practice, the terms IDZ (conceptual design) and IDP (conceptual project) are also used. These are earlier conceptual bases with which the investor and the designer verify the basic solution, for example the size, siting, functional layout and main technical possibilities. Such bases can be very useful for preparing a more realistic cost estimate and a high-quality DIIP, even though the applicable regulation does not define them under these designations as separate types of documentation for official procedures.
The sequence for preparing investment and project documentation
The preparation of a project generally proceeds according to the following logic:
- The investor defines the problem, needs, objectives and basic scope of the investment.
- The designer or other experts prepare an initial technical basis, such as an IDZ or an IDP, and on that basis also an indicative cost estimate.
- On this basis, the DIIP is produced and the decision on the further preparation of the project is taken.
- If a PIZ is required, the options are compared in greater detail and the most suitable solution is selected.
- The selected solution is further developed in the project documentation, while at the same time the value, deadlines and sources of financing are determined more precisely.
- Once the data are sufficiently reliable, the IP is prepared as the basis for the final investment decision.
- The project documentation is developed to the level required for permits and for carrying out the construction.
This sequence is not entirely the same for all projects. Project and investment documentation are often prepared partly in parallel. What matters, however, is that the data between them are consistent. Areas, quantities, costs, VAT, the timetable, the sources of financing and the content of the project must not be presented differently in the DIIP or IP than in the designer's bases and the application documentation.
Where TERRA VERDE helps
TERRA VERDE d.o.o. prepares the DIIP, PIZ and IP and brings together the data of the investor, the designer and the finance function into a consistent whole. We verify whether the technical solution supports the objectives of the project, whether the cost estimate derives from appropriate bases, whether the financing structure is feasible, and whether the documentation takes account of the conditions of the funding call or the financier.
We do not replace the designer in the technical design. Our contribution is to define in good time which data are needed, to flag any inconsistencies, and to ensure that the technical, financial and substantive parts of the project are aligned with one another.
For this reason, it is not sensible to begin preparing the DIIP or IP a few days before the deadline for submitting an application. A high-quality document requires a sufficiently clear solution, realistically estimated costs, agreed sources of financing and a feasible timetable. With early engagement, there are fewer subsequent corrections, and the investor knows in good time which bases are still required and who must prepare them.
Describe your project to us briefly, and we will check which documentation you need and how to link it to the funding call.
Sources used in preparing this article
- Uredba o enotni metodologiji za pripravo in obravnavo investicijske dokumentacije na področju javnih financ, Uradni list RS, št. 60/06, 54/10 in 27/16.
- Pravilnik o projektni in drugi dokumentaciji ter obrazcih pri graditvi objektov, Uradni list RS, št. 30/23.
- Ministrstvo za okolje in prostor, Prostorski informacijski sistem: Projektna dokumentacija.
- Ministrstvo za okolje in prostor, Prostorski informacijski sistem: Projektant.
- Gradbeni zakon (GZ-1), Uradni list RS, št. 199/21 s spremembami.